C-Train

From Wikipedia, the free encyclopedia

Jump to: navigation, search
C-Train
Locale Calgary, Alberta
Transit type Light rail transit [1]
Began operation May 25, 1981
System length 44.8 kilometres
No. of lines 3
No. of stations 37
Daily ridership 271,100
Track gauge 4 ft 8½ in (1,435 mm) (standard gauge)
Operator Calgary Transit

C-Train is the light rail transit (LRT) system in Calgary, Alberta, Canada. It has been in operation since 1981. Operated by Calgary Transit, the system currently consists of two major routes on 44.8 km (28 miles) of track, running into the southern, northwestern, and northeastern sections of the city. Currently there are also plans to build additional lines running to the west, north and the southeast of the city. Most track is at grade with its own right of way. The downtown portion is shared right of way. 8% of the system is underground, and 5% is grade separated (elevated). Trains are powered by overhead electric wires and pantographs. In the early 2000s, Calgary Transit began using the spelling CTrain for the LRT system, although this variation has not passed into general use and local media continue to use C-Train.

The CTrain has a higher ridership than any other light-rail system in North America[1] with an average of 271,100 boardings per weekday in the fourth quarter of 2007, compared to 258,100 for Toronto, Ontario and 257,500 for Boston, Massachusetts, the second and third ranking light rail systems.[2]

Contents

[edit] History

The first line of the C-Train opened on May 25, 1981 following three years of track work. This line, the 'South Line', ran from 8th Street SW station in downtown Calgary south to Anderson Station (see South Line below for details). The other two sections of the system, the Northeast Line and the Northwest Line, opened on April 27, 1985 and September 17, 1987 respectively. Since those opening dates, seven new stations have been added:

  • August 31, 1990 - Brentwood Station (Northwest Line)
  • October 9, 2001 - Canyon Meadows Station and Fish Creek-Lacombe Station (South Line)
  • December 15, 2003 - Dalhousie Station (Northwest Line)
  • June 28, 2004 - Shawnessy Station and Somerset-Bridlewood Station (South Line)
  • December 17, 2007 - McKnight-Westwinds Station (Northeast Line)

The system initially used Siemens-Duewag U2 LRVs (originally designed for German metros, and used by Edmonton's earlier ETS light railway and the U-Bahn, a light rail system in Frankfurt), which constituted the entire fleet until mid-July 2001, when the first cars of the newer Siemens SD-160 trains began arriving. There are now sixty-six SD-160s and eighty U2s in service (the eighty-third U2 was lost in a March 2001 accident, the eighty second was lost in an accident in late 2006, the eighty-first was lost in late 2007/early 2008).

Somerset-Bridlewood station on the south C-Train line.
Somerset-Bridlewood station on the south C-Train line.

However, demand for light rail has exploded in recent years. In the decade prior to 2006, the city's population grew by 25% to over 1 million people, while ridership on the C-Train grew at twice that rate, by 50% in only 10 years. This resulted in severe overcrowding on the trains and demands for better service. In December 2004, city council approved an order for 33 additional SD-160 vehicles from Siemens, and in December 2006, approved an order for an additional 7. In November 2007 city council approved purchasing another 34 SD-160 LRV's to be used in conjunction with the West LRT and further expansions to the NE and NW legs. When all are finally delivered, the city's fleet will include 223 light rail vehicles. At that point in time the city will increase the frequency of trains from one every 5 minutes to one every 3 minutes during rush hour.

As of 2007 there is a total of 44.8 km of track; the three lines are 20.7 km (the southern line or A-Line), 12.5 km (the northeastern line or B-Line), and 11.0 km (the northwestern line or C-Line) in length.

In 2001, the C-Train became the first public transit system in Canada to claim all of its electricity from emissions-free wind power generation. The electricity is generated by TransAlta operating in the southernmost region of Alberta. The trains are powered from the same power grid as before; however, an equivalent amount of electricity is produced at the southern wind farms and "dedicated" to the C-Train. Under Alberta's free market for electricity, large consumers can contract to purchase their electricity from a specific vendor, although the individual electrons received off the province-wide grid may not be exactly the same as those transmitted. The only requirement is that supply and demand be the same at each end.

In the following section preliminary timelines for construction of future stations are referenced. For example, construction of a north C-Train line is not expected until after 2023. It should be noted that the city has, on several occasions, accelerated construction of C-Train expansion due to demand and available money. For example the McKnight-Westwinds station, which opened in 2007, was, as recently as 2002, not planned until beyond 2010. Similarly, the timeline of construction of the south line extension was also pushed up several years due to increasing population and traffic volume.

[edit] Fares

Fare Type Price (Canadian dollars)[3]
Cash Fare $2.50
Youth Cash Fare $1.50
Book of 10 Tickets $21.00
Book of 10 Youth Tickets $13.00
Day Pass $6.75
Youth Day Pass $4.50
Monthly Pass $75.00
Youth Monthly Pass $50.50
Monthly Pass, Reduced Rate $37.50
Senior Citizen Annual Pass $35.00
Senior Citizen Annual Pass, Reduced Rate $15.00

[edit] Route details

Calgary Light Rail System Map
Calgary Light Rail System Map

There are currently two major routes in operation: Route 201 (Somerset/Bridlewood–City Centre–Dalhousie) and Route 202 (McKnight/Westwinds–City Centre).

[edit] Route 201

This route comprises two lines: the South Line, which was the first of the three lines to be built, and the Northwest Line, which is the newest of the three lines to be built. Currently there are eleven stations on the South line (of which two opened on 28 June 2004) and seven on the Northwest line.

[edit] South Line

Seven stations on this line opened on May 25, 1981, as the first light railway line to serve the city. From north to south, they are Victoria Park/Stampede (originally Stampede), Erlton/Stampede (originally Erlton), 39 Avenue (originally 42 Avenue), Chinook, Heritage (also the site of the Haysboro LRT Storage Facility), Southland, and Anderson (also the site of the Anderson LRT Yards). On October 9, 2001, two new stations were added: Canyon Meadows and Fish Creek-Lacombe. On June 28, 2004, two more stations opened: Shawnessy and Somerset-Bridlewood. A further two stations -- Silverado (most likely in the area of 194th Avenue SW) and near 212th Avenue South (likely sharing the name of a future community in that area) -- are planned for the future once the community of Silverado in the south is developed, likely beyond 2020.[4]

[edit] Northwest Line

Five stations on this line opened on September 7, 1987. From the most central to the most northwesterly, they are Sunnyside, SAIT/ACAD/Jubilee (the station name in full is "Southern Alberta Institute of Technology/Alberta College of Art and Design/Jubilee Auditorium"), Lions Park, Banff Trail, and University. On August 31, 1990, Brentwood station was opened as a new terminus, and on December 15, 2003, Dalhousie Station was opened. An eighth station - Crowfoot (formerly Crowfoot-Centennial) - is currently under construction and will open in late 2008,[5] and a ninth station - Tuscany-Rocky Ridge - was approved in November 2007 for completion by 2011.[6] An intermediate station near Northland Drive is possible in the future as well (between Brentwood and Dalhousie).

[edit] Route 202

This route comprises one line: the Northeast Line. All seven of these stations opened on April 27, 1985; from most central to most northeastern, they are: Bridgeland/Memorial, Zoo, Barlow/Max Bell, Franklin, Marlborough, Rundle, and Whitehorn. An eighth station - McKnight/Westwinds - opened in 2007. Two more stations - expected to be named Martindale and Saddletowne[4] - were approved in November 2007 for completion by 2011,[6] and additional stations in the 60th Street NE corridor are proposed beyond 2023 in currently undeveloped land (locations undetermined)[4] as those areas develop.[7]

[edit] Future lines

Map of the CTrain with extensions planned and under construction
Map of the CTrain with extensions planned and under construction

Plans exist to build two additional lines from the city centre: a westbound line (which would serve as an extension to Route 202), and a southeastern line (which will likely be called Route 203). A third, northern line is to be planned beyond 2023, and will likely be called Route 204. A possible Route 205 spur is also planned, which would branch off of Route 202 and travel to the Calgary International Airport. Note: station names listed below are subject to change (as Calgary Transit has, on several occasions in the past, renamed approved stations prior to construction).

[edit] West Line

The plans for this line, which runs west from downtown, have existed since the beginning of construction of the South Line in 1978.[8] It is now expected to begin construction in early 2009 and will open sometime in 2012 in the Bow Trail and 17th Avenue SW corridors.[4] The City of Calgary began a review process in late 2006 to update the plans to current standards, and Calgary City Council gave final approval to the project[9] and allocated the required $566-million project funding on 20 November 2007.[6] Funding for the project will be sourced from the infrastructure fund that was created as a result of the Province returning the education tax portion of property taxes to the city. Construction of this line will begin in early 2009 and will be constructed at the same time as the extensions of the NE and NW lines of the LRT system that were approved in November 2007.

The original plan called for seven stations; the first station in the Downtown core at 11th Street has since been removed from the West LRT project and will be included in the 7th Avenue redevelopment project instead. The six remaining stations are expected to be named (from east to west): Sunalta (near 18th Street S.W.), 26th Street West (Shaganappi), Westbrook, 45th Street West (Glendale), Signal Hill, and College (west of 69th Street S.W. near Westside Recreation Centre).

The updated alignment from the 2007 West LRT Report[4] includes the line running on an elevated guideway beginning to the west of the future 11th Street Station, running along Bow Trail S.W. to 24th Street S.W. The line will then run at grade past 26th Street Station and drop into a tunnel to 33rd Street SW. The tunnel will then run across the Westbrook Mall parking lot, and under the current site of Ernest Manning Senior High School. The line will then follow the north side of 17th Avenue S.W. past 37th Street S.W. either below grade, or above grade (the final decision will be made during the design/build process) to 45th Street Station. Past 45th Street the line will run at grade, and approaching Sarcee Trail S.W. will move onto an elevated guideway that will pass over Sarcee Trail. The line will then run at grade until the Signal Hill Station, and will then proceed to drop below grade and pass under 17th Avenue S.W. at 69th Street S.W. and return to grade on the south side of the avenue. The line will then terminate at the site of the final station located to the west of 69th Street S.W. (tentatively known as College Station due to the proximity to two private colleges that are located adjacent to the station).[10]

It is also possible that the line may eventually continue as far west as 85th Street West (or even 101st Street West) in the future as those areas are built out. All stations, with an exception of Westbrook, which will be located below grade, and the 18th Street Station which will be elevated, will be located at grade.

[edit] Southeast Line

This line is planned to run from downtown (although on a different routing, not following the 7th Avenue corridor) to the communities of Douglasdale and McKenzie Lake and McKenzie Towne in the southeast, and onwards past Highway 22X into the so-called "Homesteads" region east of the Deerfoot Trail extension. Seventeen stations have been planned for this route, of which up to eleven are expected to be built by 2023. Three of the proposed downtown stations are expected to be built underground[11], and the rest of the line will follow the 52 Street SE corridor from Douglasdale and McKenzie Towne to Auburn Bay (south of Highway 22X) and then wind its way through Health Campus (adjacent to a planned southeast hospital) and Seton. Unlike Lines 201 and 202, which use high-floor U2 and SD-160 LRVs, Line 203 is expected to employ low-floor LRVs[12], such as the Siemens Avanto.

From north to south, the proposed stations are: Eau Claire, Central (at 6 Avenue), Macleod Trail, 4 Street SE, Ramsay/Inglewood, Crossroads, Highfield, Lynnwood, Ogden, South Hill, Douglasdale (the last expected by 2023), Shepard, Prestwick, McKenzie Towne, Auburn Bay, Health Campus (the station likely will share the name of the hospital), and Seton, with further stations to the south expected in the future.[13]

[edit] North Line and Airport Spur

Although it is not expected to be built until beyond 2023, this line (for which a route has not yet been determined) would likely go to serve the Country Hills community and go as far as the planned Stoney Trail beltway. The only part of the north line whereby an alignment has been determined is the portion that will follow Harvest Hills Boulevard north from Beddington Trail and a terminus. In addition, an airport spur (which could include a connection with a proposed high-speed rail service to Edmonton) is also possible, hence creating two lines running concurrently from 64th Avenue NE through to downtown.[14]

[edit] Other future improvements

Although newer models have been purchased, almost all of Calgary's original trains remain in service.
Although newer models have been purchased, almost all of Calgary's original trains remain in service.

Currently, Calgary Transit operate three-car trains. The four newest stations—Dalhousie, McKnight-Westwinds, Shawnessy, and Somerset-Bridlewood along with the 1st Street W station in Downtown—have been built to accommodate trains of four cars, and it is planned to expand the original stations to support four cars. The downtown stations and the South Line will be upgraded first, ending in 2013; followed by the Northwest Line (so as to be able to run four-car trains on Route 201) in 2015 and the Northeast Line in 2017. By 2023 Calgary Transit also plans to begin replacing some of the original Siemens-Duewag U2s (as of 2004 eighty-two of the original eighty-three are in service, and are nearing twenty-three years of service, and by 2023 will be forty-two years old). Ultimately, 40 new SD160 model C-train cars will be in service by the end of 2007. Twenty-six of them have already come into service so far.

[edit] Downtown station refurbishment

In June 2007 the City of Calgary released information on the schedule for the refurbishment of the downtown stations.[15] The plan involves replacing and relocating a number of the stations, and expanding other stations (such as Centre Street which was refurbished in 2001) to allow for four-car trains. Many of the new stations will keep their existing names, however they may be shifted one block east or west, or to the opposite side of 7th Avenue SW. The first station to undergo refurbishment will be the 7th Street SW station, which will be relocated one block to the east. The 6th Street SW and 4th Street SW Stations will be reconstructed in place. This does require that the stations be closed for a period of time while the work is undertaken, however only one station will be closed at any given time. The new stations will feature longer platforms for longer trains, better integration of the platforms into the sidewalk system, better lighting, and more attractive landscaping and street furniture.

The 10th Street SW Station, which is currently the terminus for Route 202 in the downtown, will be replaced with a new station located one block to the west at 11th Street SW. This station was initially proposed to be undertaken as the first station to be completed in the refurbishment project, however it has been pushed back and will now be completed closer to 2012 and the opening of the West LRT.

[edit] Underground infrastructure

Although it initially planned to build most of the downtown portion underground[16], and actually built some tunnels which still exist, the city deferred the plans due to the high costs and an economic recession. It also discovered that the surface system could accommodate higher passenger volumes than expected without incurring the costs of a tunnel. As a result of the original plans, when it built a new Municipal Building, it built an incomplete LRT station beneath it and a short section of tunnel leading to it under 8th Avenue S. The turnoff to this station is visible in the tunnel on Route 201 entering downtown from the south, shortly before City Hall. However, after urban explorers discovered the tunnel and visited it during a transit strike, the city walled off the spur tunnel with cinder blocks. The underground station it connects to still exists, although it is not open to the public.

As the population of metropolitan Calgary increases and growing suburbs require new lines and extensions, the higher train volumes will exceed the ability of the downtown section along 7th Avenue S to accommodate them. To provide for long-term expansion, the city is reviewing its plans to put parts of the downtown section underground. The current plans allow the expanded Route 202 (Northeast/West) to use the existing 7th Avenue S surface infrastructure. The expanded Route 201 (Northwest/South), currently sharing 7th Avenue S with Route 202, will be relocated to a new tunnel dug beneath 8th Avenue S. The future Southeast/Downtown route will probably enter downtown through a shorter tunnel under one or more streets (candidates include 2nd Street W, 5th Street W, 6th Street W, 8th Avenue S, 10th Avenue S, 11th Avenue S, and 12th Avenue S). The future North line will probably share track from the Zoo through downtown with the existing Northeast line (Route 202), avoiding the cost of a tunnel until passenger volumes grow too high.[13] Although Calgary City Council commissioned a functional study for the downtown metro component of the C-Train system in November 2007, the city is unlikely to complete this expansion before 2017 unless additional funding is received from provincial or federal governments.

[edit] List of C-Train stations

The typical C-Train station outside the downtown core allows for several methods of passenger arrival and departure. Many C-Train passengers travel to and from suburban stations on feeder bus routes that wend their way through surrounding neighbourhoods. Another popular option is a Park and Ride lot, in which commuters drive to a station by car and then transfer to a C-Train to complete their journey. Alternatively, some C-Train passengers disembark at drop-off zones from vehicles travelling elsewhere; because many of these commuters are conveyed by their spouses, these zones are branded as Kiss and Ride areas.

[edit] Route 201

Station Route Area Open Location
Dalhousie Route 201 NW 2003 51°06′12″N 114°09′39″W / 51.10333, -114.16083 (Dalhousie)
Brentwood Route 201 NW 1990 51°05′15″N 114°07′56″W / 51.0875, -114.13222 (Brentwood)
University Route 201 NW 1987 51°04′49″N 114°07′23″W / 51.08028, -114.12306 (University)
Banff Trail Route 201 NW 1987 51°04′15″N 114°06′55″W / 51.07083, -114.11528 (Banff Trail)
Lions Park Route 201 NW 1987 51°03′54″N 114°06′12″W / 51.065, -114.10333 (Lions Park)
SAIT/ACAD/Jubilee Route 201 NW 1987 51°03′47″N 114°05′28″W / 51.06306, -114.09111 (SAIT)
Sunnyside Route 201 NW 1987 51°03′21″N 114°05′03″W / 51.05583, -114.08417 (Sunnyside)
8th St. SW Route 201, 202 Downtown 1981 51°02′49″N 114°04′52″W / 51.04694, -114.08111 (8th St.)
6th/7th St. SW Route 201, 202 Downtown 1981 51°02′48″N 114°04′30″W / 51.04667, -114.075 (7 Street)
3rd/4th St. SW Route 201, 202 Downtown 1981 51°02′48″N 114°04′13″W / 51.04667, -114.07028 (3 Street)
1st St. SW/Centre St. Route 201, 202 Downtown 1981 51°02′48″N 114°03′51″W / 51.04667, -114.06417 (Centre Street)
Olympic Plaza/City Hall Route 201, 202 Downtown 1981 51°02′47″N 114°03′29″W / 51.04639, -114.05806 (Olympic Plaza)
Victoria Park/Stampede Route 201 S 1981 51°02′18″N 114°03′30″W / 51.03833, -114.05833 (Stampede)
Erlton/Stampede Route 201 S 1981 51°01′56″N 114°03′31″W / 51.03222, -114.05861 (Erlton)
39th Avenue Route 201 S 1981 51°01′03″N 114°03′42″W / 51.0175, -114.06167 (39th Avenue)
Chinook Route 201 S 1981 50°59′50″N 114°03′58″W / 50.99722, -114.06611 (Chinook)
Heritage Route 201 S 1981 50°58′43″N 114°04′27″W / 50.97861, -114.07417 (Heritage)
Southland Route 201 S 1981 50°57′51″N 114°04′36″W / 50.96417, -114.07667 (Southland)
Anderson Route 201 S 1981 50°57′17″N 114°04′29″W / 50.95472, -114.07472 (Anderson)
Canyon Meadows Route 201 S 2001 50°56′10″N 114°04′12″W / 50.93611, -114.07 (Canyon Meadows)
Fish Creek-Lacombe Route 201 S 2001 50°55′23″N 114°04′22″W / 50.92306, -114.07278 (Fish Creek)
Shawnessy Route 201 S 2004 50°54′38″N 114°04′14″W / 50.91056, -114.07056 (Shawnessy)
Somerset-Bridlewood Route 201 S 2004 50°53′57″N 114°04′09″W / 50.89917, -114.06917 (Somerset)

[edit] Route 202

Station Route Area Open Location
10th St. SW Route 202 Downtown 1985 51°02′49″N 114°04′58″W / 51.04694, -114.08278 (10th St.)
8th St. SW Route 201, 202 Downtown 1981 51°02′49″N 114°04′52″W / 51.04694, -114.08111 (8th St.)
6th/7th St. SW Route 201, 202 Downtown 1981 51°02′48″N 114°04′30″W / 51.04667, -114.075 (7 Street)
3rd/4th St. SW Route 201, 202 Downtown 1981 51°02′48″N 114°04′13″W / 51.04667, -114.07028 (3 Street)
1st St. SW/Centre St. Route 201, 202 Downtown 1981 51°02′48″N 114°03′51″W / 51.04667, -114.06417 (Centre Street)
Olympic Plaza/City Hall Route 201, 202 Downtown 1981 51°02′47″N 114°03′29″W / 51.04639, -114.05806 (Olympic Plaza)
3rd St. SE Route 202 Downtown 1985 51°02′46″N 114°03′17″W / 51.04611, -114.05472 (3rd St SE)
Bridgeland/Memorial Route 202 NE 1985 51°02′56″N 114°02′26″W / 51.04889, -114.04056 (Bridgeland)
Zoo Route 202 NE 1985 51°02′51″N 114°01′30″W / 51.0475, -114.025 (Zoo)
Barlow/Max Bell Route 202 NE 1985 51°02′45″N 114°00′25″W / 51.04583, -114.00694 (Barlow)
Franklin Route 202 NE 1985 51°02′50″N 113°59′38″W / 51.04722, -113.99389 (Franklin)
Marlborough Route 202 NE 1985 51°03′32″N 113°58′54″W / 51.05889, -113.98167 (Marlborough)
Rundle Route 202 NE 1985 51°04′30″N 113°58′54″W / 51.075, -113.98167 (Rundle)
Whitehorn Route 202 NE 1985 51°05′11″N 113°58′54″W / 51.08639, -113.98167 (Whitehorn)
McKnight-Westwinds Route 202 NE 2007 51°05′52″N 113°58′54″W / 51.09778, -113.98167 (McKnight-Westwinds)

[edit] Future Stations

Station Route Area Open Location
Crowfoot Route 201 NW late 2008 51°07′23″N 114°12′27″W / 51.12306, -114.2075 (Crowfoot)
Tuscany-Rocky Ridge Route 201 NW 2011 51°08′07″N 114°14′15″W / 51.13528, -114.2375 (Tuscany-Rocky Ridge)
Martindale Route 202 NE 2011 51°07′11″N 113°57′39″W / 51.11972, -113.96083 (Martindale)
Saddletowne Route 202 NE 2011

51°07′30″N 113°56′54″W / 51.125, -113.94833 (Saddle Ridge)

69th St. SW Route 202 West 2012-2013 51°02′15″N 114°11′26″W / 51.0375, -114.19056 (69th St.)
Sirocco Drive SW Route 202 West 2012-2013 51°02′13″N 114°10′17″W / 51.03694, -114.17139 (Sirocco Drive)
45th St. SW Route 202 West 2012-2013 51°02′16″N 114°09′12″W / 51.03778, -114.15333 (45th St.)
Westbrook Route 202 West 2012-2013

51°02′23″N 114°08′17″W / 51.03972, -114.13806 (Westbrook)

26th St. SW Route 202 West 2012-2013 51°02′29″N 114°07′24″W / 51.04139, -114.12333 (26th St.)
Sunalta Route 202 West 2012-2013 51°02′41.28″N 114°05′56″W / 51.0448, -114.09889 (16th St.)

[edit] See also

Wikimedia Commons has media related to:

[edit] References

  1. ^ Calgary Transit (2006). Calgary’s CTrain – Effective Capital Utilization. City of Calgary. Retrieved on 2008-02-11.
  2. ^ Public Transportation Ridership Statistics. American Public Transportation Association (2008). Retrieved on 2008-03-20.
  3. ^ http://www.calgarytransit.com/html/fares.html
  4. ^ a b c d e Calgary Transportation Planning (November 20, 2007). "2007 West LRT Report" (PDF). City of Calgary. Retrieved on 2007-12-22.
  5. ^ Calgary Transportation Infrastructure (2007). Northwest LRT Extension - Dalhousie CTrain Station to Crowfoot CTrain Station. City of Calgary. Retrieved on 2007-12-22.
  6. ^ a b c Calgary City Council (2007). Minutes of Calgary City Council special meeting of 06 November 2007 (MS Word). City of Calgary. Retrieved on 2007-12-22.
  7. ^ Calgary Land Use Planning & Policy (2007 July). "Northeast Community 'A' Structure Plan" (PDF). City of Calgary. Retrieved on 2007-12-22.
  8. ^ Calgary Transportation Department (1983). "West LRT Functional Study" (PDF). City of Calgary. Retrieved on 2007-12-22.
  9. ^ CBC News. "Council confirms route for C-Train's west line", Canadian Broadcasting Corporation, November 20, 2007. Retrieved on 2007-12-22. 
  10. ^ City of Calgary. West LRT Map [map], 2007 edition. Retrieved on 2007-12-22.
  11. ^ Calgary Land Use Planning & Policy (2007). "City Centre Plan" (PDF). Part 2, p. 79. City of Calgary. Retrieved on 2007-12-22.
  12. ^ Calgary Land Use Planning & Policy (2007). "Beltline Area Redevelopment Plan" (PDF). Part 2, pp. 85-86. City of Calgary. Retrieved on 2007-12-22.
  13. ^ a b Clifton ND Lea Consulting (2004). "Southeast LRT Functional Planning Study" (PDF). Phase III - Glenmore Trail to Elbow River. City of Calgary. Retrieved on 2007-12-22.
  14. ^ Calgary Transit (2006). "North Central Calgary Transit Corridor Review" (PDF). City of Calgary. Retrieved on 2007-12-22.
  15. ^ Calgary Transportation Infrastructure (2007). 7 Avenue Refurbishment. City of Calgary. Retrieved on 2007-12-22.
  16. ^ Calgary Planning Department (1982). "City Hall Area Redevelopment Plan" (PDF). p. 30. City of Calgary. Retrieved on 2007-12-22.

[edit] External links

Personal tools