Background:- Bandra is one of the major suburban stations in Mumbai. More than thousand suburban trains operation take place every day about 5 lacks commuters traveling through this station. Out of this 39% commuters approach the station by walk while 32% by bus 16% by Auto and 13% by other modes. The percentage to the station is nearly equal on the East and West. With the development of Bandra-Kurla Complex into last few years the commuters from BKC have substantial increased. Further, the Western Railway is developing the Bandra Terminal about 1 km north of the suburban station and operations from this terminal are also increasing every year above.
Bandra SATIS:- The considering the Bandra Station Area Traffic Improvement Scheme has been included in the priority works under MUIP master plan. After considering several alternatives it is decided to develop Skywalks from Bandra (E) to Kalanagar and Bandra (W) to Hill road and Mohd. Raffi Chowk on priority. Skywalk form Bandra (E) to Kalanagar has been completed as pilot project.
General features of the Skywalk:- The Skywalk between Bandra Station from (Existing Foot Over Bridge to Kalanagar has been constructed to serve the commuters traffic between BKC and the Station.) The work included construction of Skywalk form Bandra suburban railway Foot Over Bridge to Kalanagar. It is 1300 m. long and 4 m. wide walk way and 4 staircase at various locations. This Skywalk proposed is covered by multi wall polycarbonate sheet for weather protection to the pedestrian. The integration arrangements with the railway for provision of ticket counter, if required by railway are being finalised.
The general features are as follows:-
- Length of the Skywalk – 1300 m.
- Width of the Skywalk – 4.0 m. clear walkway
- Structural details – The Skywalk construction consists of elevated walkway of 4.0x3.0 m. framed structure with Polycarbonate Sheet as roofing and resting on 1.0 m. dia. Pier of ht. approximately 6.0 m. above the ground level.
- No. of Staircase – 4 Nos.
- Staircase location – Anant Kanekar Marg Police Chowki, Near ONGC Building, Kalanagar on either side of Sion-Dharavi Road.
Integration Arrangement:- (Station end) Integration with exiting Foot Over Bridge has been planned by directly connecting to the Foot Over Bridge. A provision to connect to the exiting southern Foot Over Bridge (platform 6/7)
Integration array (Kalanagar end):- Staircase is proposed on either side of Soin-Dharavi Lind Road to integrate with existing BEST Bus Stops.
Current Status:- The Project have been completed and opened to public with effect from 24th June, 2008.
Contractor :- M/S. DAS Offshore
Consultant :- M/S. S. N. Bhobe Associates
Period of construction:- 27th Dec. 2007 to 24th June 2008