Mumbai Urban Transport Project

As a sequel to the Bombay Urban Transport Project (BUTP) which was completed in the year 1984 at a cost of about Rs. 390 million, the MMRDA has formulated a multi modal project viz Mumbai Urban Transport Project (MUTP) to bring about improvement in traffic and transportation situation in the MMR with the World Bank assistance. MUTP envisages investment in suburban railway projects, local bus transport, new roads, bridges, pedestrian subways and traffic management activities. Mumbai Rail Vikas Corporation (MRVC), a joint venture of Railways and Government of Maharashtra, is set up for implementation of rail projects under MUTP and other projects of Railways in the MMR.

The total estimated cost of the project is Rs. 45260 million ($ 943 million )

The World Bank has sanctioned a loan of Rs. 26020 millions ($ 542 million) i.e. 57% of the total cost on 18th of June 2002.

Some facts and figures

  • Over 88% of the commuters in Mumbai travel by suburban trains or BEST buses.
  • Mumbai's Suburban Rail System carries about 64 lakhs (6.4 million) passengers per day.
  • About 4700 passengers travel in a 9-car rake during peak hours, as against its rated carrying capacity of only 1,700.

Partners in MUTP -

* Government of Maharashtra shares 50% cost of the Rail Component or Rs. 17550 million.
* MMRDA provides counter part funds of Rs. 7450 million on behalf of Govt. of Maharashtra.

 
Project Components and Costs
 
No. Component
Project
affected
families
Cost
(inclusive of R&R)
(Rs. In Millions)
A Road Transport Components
1 Jogeshwari-Vikhroli link road
890

1680

2 Santacruz-Chembur link road
including an ROB at Kurla
2171
1870
3 ROB at Jogeshwari (South)*
901
800
4 ROB at Jogeshwari (North)*
514
540
5 ROB at Vikhroli*
173
370
6 Purchase of around 500 eco friendly buses
-
1130
7 Pedestrian Grade Separation
Schemes
-
730
8 Area Traffic Control System in the Island City
-
720
9 Station Area Traffic Improvement Schemes (SATIS) at 6 stations*
-
730
10 Other Traffic Management and safety schemes including footpaths
-
550
11 Environment - Air quality monitoring
-
130
12 Different studies and Technical Assistance
-
910
  Sub-total
4649
10160
B Rail Transport Components
1 5th line on Western Railway between Mahim and Borivali
515
740
2

5th and 6th lines between Kurla and Thane

 
 
3

Borivli-Bhayandar additional pair of lines (including Virar car shed and Virar - Dahanu road track centre work)

 
 
4 Optimisation on Western Railway
 
 
5 Optimisation on Central Railway
 
 
6 Optimisation on Harbour line
 
 
7

DC/AC conversion

 
 
8 Procurement of new EMUs (trains)
 
 
9 EMU maintenance facilities
 
 
10

Stabling lines

 
 
11 Track machines
 
 
12 Technical assistance and studies
 
 
13 PPF reimbursement    
  Sub-total
14479
35100
Grand total
19128
45260
 

Project Implementation Period : 2002 to 2009
* Excluded by World Bank from MUTP during re-structuring of project (July 2008)

Project Benefits

  • 35% extra carrying capacity in suburban trains during peak period.
  • Less crowd in coaches : Reduction from 4700 passengers to around 3000 passengers per 9 car rakes in peak hours.
  • Higher frequency of train Services
  • Reduction in journey time
  • Running or EMUs on Virar - Dahanu Road section
  • Introduction of new EMU coaches with smoother riding facilities better light and ventilation bigger windows, higher acceleration and deceleration and less noise.
  • Increase in carrying capacity of BEST buses.
  • Reduction in traffic congestion and increase in vehicular speed on roads.
    Safe and smooth flow of vehicular and pedestrian traffic.
  • Improvement in the flow of passengers and vehicles in and around selected stations.
  • Minimising delays and accidents.
  • Reduction in air Pollution.
  • Rehabilitation and Resettlement of 19,128 poor families.

Resettlement and Rehabilitation (R&R) of project affected persons

  • 19,128 households / structures affected by MUTP (Road and Traffic Component - 4649 Rail Component - 14479)
  • A Resettlement Action Plan (RAP) prepared for rehabilitation of all the PAPs
  • Site Specific Resettlement Implementation Plans (RIP) for individual sub projects.
  • Rehabilitation to be done as per the provisions of the R and R Policy for MUTP, 1997 formulated by Government of Maharashtra and endorsed by the Indian Railways.
  • Each eligible project affected family to get a tenement of 225 sq. ft. free of cost.
  • Transit accommodation of 120 sq.ft. with all basic amenities when urgent shifting is required.
  • Rehabilitation with active involvement of NGOs and participation of the community.
  • Total cost of rehabilitation Rs. 4678 million.
    Out of total 19128 PAPs, 17800 PAPs already rehabilitated by March 2008

Rail Components

Western Railways 5th line - Borivali to Mahim

  • Scope
    • 5.5 Kms to track from Santacruz to Mahim
    • Modification to Harbour Line flyover near Mahim
  • Cost : Rs. 59 crores.
  • R&R: 151 (in Borivali Santacruz section)
  • Present Status
    • The line from Santacruz to Borivali has been laid and 151 PAP have been resettled.
  • Benefits
    • Complete segregation of main line and suburban trains during the peak hours in Borivali - Mumbai Central section.
    • 8 additional paths for suburban trains during the morning peak hours.

Top

Kurla - Thane additional pair of tracks

  • Scope
    • Additional pair of tracks 18 Kms from Thane to Kurla
  • Cost : Rs. 166 crores
  • R&R 2986
  • Present Status
    • The work is already in progress and about 50% complete. 1969 PAPs have already been resettled. Total expenditure upto June 2008 Rs. 138.27 crores and outlay for 2008-2009 Rs. 35 crores.
  • Benefits
    • Segregation of main line and suburban train in Kurla - Thane section.
    • All main line Passenger trains to or from Kurla terminus and fright trains to or from Trombay or Kurla yard will not interfere with suburban train operation in CSTM - Thane section.

Top

Borivali - Virar Additional pair of tracks

  • Scope.
    • Additional pair of tracks 26 Kms from Borivali to Virar.
    • Setting up EMU maintenance shed at Virar.
    • Major bridge (2.0 Kms in two stretches) at Vasai creek
  • Cost : Rs. 509 crores
  • R&R : 501
  • Present Status
    • The work is completed. 105 PAPs have already been resettled. Total expenditure upto June 2008 Rs. 488 crores
  • Benefits
    • Almost double carrying capacity during peak hours in Virar - Borivali section, which is the second heaviest section in Mumbai suburban network.

Top

Road Components

Jogeshwari Vikroli Link Road (JVLR)

JVLR is one of the five major East - West links proposed in suburbs to connect Western Express Highway and Eastern Express Highway. This link road is existing today. However, at present it has 2 - lane carriage way which is inadequate. It is proposed to widen this road to 6 - lane divided carriage way with a right-of-way of about 35 meters. Two flyovers are being constructed along the link road by MSRDC. The cost of this project is estimated at Rs. 1680 million. In all 1201 PAHs will be affected by this project.

Top

Pedestrian Grade Separation Schemes

In order to provide safe and exclusive pedestrian crossing and to reduce vehicular delay due to pedestrian signals, Pedestrian Grade Separation Schemes are proposed at 30 major intersections and mid block in the Island City and Suburbs. The estimated cost of these works is Rs. 709.44 million.

Top

 
Implementing Agencies and their Responsibilities
 
No. Organisation Functions
1 MMRDA

Contact Person:
Additional Metropolitan Commissioner & Project Director, MUTP (Project Management / Monitoring Unit in MMRDA)

Address:
Bandra-Kurla Complex,
Bandra (East),
Mumbai - 400 051.

Tel. No.: 91-22-6591235

Fax No.: 91-22-6591264
Co-ordination and monitoring of the overall project. Implementation of R&R activities for rail and road transport components and some TA related to road transport component.
2 MRVC

Contact Person:
Managing Director

Address:
2nd floor, Churchgate Station Building,
Mumbai - 20

Tel.No.: 91-22-2080015

Fax No.: 91-22-2096972
Implementation of all rail projects, including co-ordination of activities of CR, WR and RDSO
3 MCGM

Contact Person:
Additional Municipal Commissioner

Address:
MCGM, Mahapalika Marg, Mumbai 400001.

Tel. No.: 91-22-2620149

Fax No.: 91-22-2626437
Traffic management, environment - air quality monitoring. construction of pedestrian subways and foot over bridges.
4 MSRDC

Contact Person:
Jt. M.D.

Address:
Priyadarshani Park, Nepean Sea Road, Mumbai - 400 036

Tel. No.: 3685910 / 3686112 / 3693671

Fax No.: 3684143
Construction of JVLR and SCLR.
5 BEST

Contact Person:
General Manager

Tel.No.: 91-22-2856262

Fax No.: 91-22-2851244

Procurement of buses.
6 MCGM for Traffic Police

Contact Person:
Jt. Commissioner of Police (Traffic)

Address:
87, Sir Pochkhanwala Road, Worli, Mumbai - 400 025

Tel.No.: 91-22-2856262

Fax No.: 91-22-2851244
Area Traffic Control Scheme.
 

List of Major projects under implementation

  • 5th line on W. Railway; Mahim Santacruz
  • Additional pair of lines between Kurla-Thane (C.Rly).
  • Additional pair of lines between Borivali -Virar (W.Rly).
  • Service efficiency improvements- Optimisation of C.Rly, W.Rly and Harbour line
  • EMU Coach Remanufacturing & new Rolling Stock (101 Nos)
  • Conversion of EMU rakes DC to AC.
  • TA and Institutional strengthening Taxes etc.
  • Roads Jogeshwari-Vikhroli Link Road, Santacruz-Chembur Link Road.
  • Area Traffic Control
  • Pedestrian Grade Separation schemes
  • Procurement of Buses (650 nos).
  • Resettlement & Rehabilitation of Project Affected Persons

Status of MUTP projects:
All the project components are in advance stage of implementation and are expected to be completed by December 2009.

In order to further improve the suburban railway services extremes of network and operations, MRVC has formulated MUTP II to be funded under the same formula of on going MUTP. Government of Maharashtra and Ministry of Railways have approved the project.

List of Proposed Mumbai Urban Transport Projects (MUTP)-II

  • Kurla-CSTM 5th & 6th lines:                                               581 Cr.
  • Thane-Diva additional pair of lines:                                     109 Cr.
  • Borivali Mumbai Central 6th Line:                                       442 Cr.
  • Ext. of harbor line to Goregaon:                                           83 Cr.
  • DC to AC conversion:                                                        239 Cr.
  • EMU procurement & manufacture:                                     2495 Cr.
  • Maintenance facilities for EMUs:                                          184 Cr.
  • Stabling lines for EMUs:                                                     114 Cr.
  • Technical Assistance and Institutional Strengthening:             50 Cr.
  • R&R;:                                                                                105 Cr.
  • Station Imp. & Trespassing Control:                                    107 Cr.
                                                                                    TOTAL : 4509 Cr.

Top

 
 
  Projects
  Bombay Urban Transport Project
  Mumbai Urban Development Project
  Shifting of Wholesale Markets
  Wadala Truck Terminal
  Mahim Nature Park
  Mumbai Urban Transport Project
  Mumbai Urban Infrastructure Project
  Mumbai Metro Rail Project
  Niramal MMR Abhiyan
  Skywalk
  Monorail
  SATIS
  Rental Housing
  SWM Special Project Cell
 
  Mumbai
Metropolitan Region
Mumbai Metropolitan Region Map